Valid Project-Management Dumps shared by EduDump.com for Helping Passing Project-Management Exam! EduDump.com now offer the newest Project-Management exam dumps, the EduDump.com Project-Management exam questions have been updated and answers have been corrected get the newest EduDump.com Project-Management dumps with Test Engine here:
A new multifamily apartment building is constructed using a construction manager at-risk delivery method. The owner is eager to begin leasing units in the building and requests that the architect sign the certificate of substantial completion without listing any work to be completed. Which party is required to sign the certificate of substantial completion?
Correct Answer: D
The AIA A201 and B101 clearly state that the architect is the one who certifies substantial completion.The architect must inspect the work and include a list of incomplete or corrective work (a "punch list") as part of the Certificate of Substantial Completion. The building inspector may issue a certificate of occupancy, but the architect is responsible for certifying substantial completion. References: AIA A201-2017 § 9.8.4 AIA G704 Certificate of Substantial Completion NCARB ARE 5.0 Handbook - Construction & Closeout Tasks