Valid Project-Management Dumps shared by EduDump.com for Helping Passing Project-Management Exam! EduDump.com now offer the newest Project-Management exam dumps, the EduDump.com Project-Management exam questions have been updated and answers have been corrected get the newest EduDump.com Project-Management dumps with Test Engine here:
An architect is evaluating a change order. Where should the costs for the project superintendent or general foreman be included?
Correct Answer: C
The costs associated with a project superintendent or general foreman are classified under field overheads. These are not directly tied to a specific construction activity (like labor laying concrete) but are necessary for managing and supervising the site work. Field overheads include site-specific expenses such as temporary facilities, safety equipment, and supervisory personnel costs. General and administrative overheads, by contrast, are associated with the contractor's home office and not directly attributable to a specific project site. Reference: NCARB ARE 5.0 Handbook - PjM Content Area 2: Project Costs & Budgeting Reference: AIA Document G701 Commentary, AIA Best Practices