Valid PDD Dumps shared by ExamDiscuss.com for Helping Passing PDD Exam! ExamDiscuss.com now offer the newest PDD exam dumps, the ExamDiscuss.com PDD exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PDD dumps with Test Engine here:
The architect has completed 60% of the construction documents. The owner wants to establish the guaranteed maximum price (GMP) at this point before 100% of the construction documents are complete. Several flooring finish items are still undetermined. What should be included in the project manual to make sure the contractor has a cost to cover all finishes?
Correct Answer: C
When a GMP (Guaranteed Maximum Price) is established before the design is 100% complete and specific materials are not yet chosen, the correct approach is to specify allowances in the project manual. An allowance is a fixed monetary amount for a specific scope item (e.g., flooring finishes) that allows the contractor to carry a cost in the bid/GMP until the actual product is selected. This ensures the GMP covers the item without delaying pricing. A). Contingency - Is for unforeseen conditions, not specific unselected finishes. B). Schedule of unit prices - Typically used for variable-quantity work, not for unknown product selection. D). Alternate - Provides an option for substitution, but does not guarantee a base cost in the GMP. PDD Reference: ARE 5.0 PDD "Project Manual and Specifications-Allowances, Alternates, and Unit Prices," AIA A201 §3.8, CSI Division 01-General Requirements.