An architect is coordinating the mechanical and structural systems in a building with exposed ceilings. The HVAC ducts are interfering with a large concrete beam in the open office area.
Correct Answer: C
In PDD, the architect must coordinate consultant drawings. When a conflict exists (here, duct vs. beam), the best course is to ask the responsible engineer (mechanical) to reroute the ductwork to clear the beam. As per ARE 5.0 Handbook Objective 3.1, the architect is expected to "coordinate building systems and their integration."