Before construction documents are complete, the owner requests a review of the timeline allowed for ASIs, RFIs, RFPs, and change orders as defined in the project manual. Which section of the project manual is relevant to this request?
Correct Answer: D
The owner's request for review of ASIs (Architect's Supplemental Instructions), RFIs (Requests for Information), RFPs (Requests for Proposals), and change orders relates to contract modifications. Section 01 26 00 in the project manual typically covers Contract Modification Procedures, including timelines and processes for handling these changes. AIA Document A201 is the general conditions but does not detail specific timelines. Supplementary Conditions modify A201 but usually don't detail these timelines. Section 01 35 16 is specific to alteration projects, not general contract mod procedures. Reference: NCARB ARE 5.0 Review Manual, Project Management chapter CSI MasterFormat and project manual organization guides