An organization Is Implementing a new electronic medical record and has employed a project manager.
At the first meeting, the project manager observes the following:
* The team estimates It Is one-fourth finished with Identifying benchmark organizations.
* Team members have not yet begun to identify the current state.
- They are halfway through collecting public data, which puts them slightly behind schedule for that task.
Which of the following tools should the quality Improvement project manager recommend?
Correct Answer: C
A Gantt chart is a type of bar chart that illustrates a project schedule1. This tool is used in project management, and it's particularly useful in the scenario described because it can help the team visualize their progress on different tasks1.
In this case, the team is at different stages with various tasks: they're one-fourth finished with identifying benchmark organizations, they haven't started identifying the current state, and they're halfway through collecting public data1. A Gantt chart can help them see all these tasks and their progress in one place, making it easier to manage their work and stay on schedule1.
While the other tools mentioned (Model for Improvement, Design of Experiments, Ishikawa diagram) can be useful in certain scenarios, they don't specifically address the need to visualize and manage progress on multiple tasks23. Therefore, the Gantt chart is the most appropriate tool to recommend in this situation1.