Valid 74-343 Dumps shared by ExamDiscuss.com for Helping Passing 74-343 Exam! ExamDiscuss.com now offer the newest 74-343 exam dumps, the ExamDiscuss.com 74-343 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 74-343 dumps with Test Engine here:
Your organization uses Project Professional 2013 and records actual hours worked on the project. You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases. The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task. You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)