Question 76/101

You are a project manager who uses Project Professional 2013.
When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table. You discover that many of the tasks have negative Total Slack values.
You need to resolve the negative Total Slack values.
What should you do?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (101q)
Question 1: You are a senior project manager, and your organization uses...
Question 2: You are a project manager who uses Project Professional 2013...
Question 3: You are a project manager who uses Project Professional 2013...
Question 4: Your company uses Project Professional 2013. You are setting...
Question 5: You are using Project Standard 2013. Management wants to see...
Question 6: DRAG DROP You are a project manager who uses Project Standar...
Question 7: You are a project manager, and your organization uses Projec...
Question 8: Your company uses Project Standard 2013 to track project pro...
Question 9: You work as a project manager for a construction company tha...
Question 10: You manage a project for an organization that uses Project P...
Question 11: You are a project manager for a company that uses baselines ...
Question 12: You are a project manager who uses Project Professional 2013...
Question 13: You are a program manager who uses Project Professional 2013...
Question 14: While creating a schedule with Project Professional 2013, yo...
Question 15: You are a project manager for a software development company...
Question 16: DRAG DROP You are an independent project manager who uses Pr...
Question 17: You are a project manager for a software development company...
Question 18: Your company uses Project Professional 2013. You have two pr...
Question 19: You are managing a project using Project Professional 2013. ...
Question 20: You are a project manager for a large telecommunications com...
Question 21: Your company uses Project Professional 2013. You have severa...
Question 22: You are a project manager, and your company uses Project Pro...
Question 23: Your organization uses Project Professional 2013 and Microso...
Question 24: You are a project manager who uses Project Professional 2013...
Question 25: You are a project manager for an organization that uses Proj...
Question 26: You are using Project Standard 2013. You want the ability to...
Question 27: Your organization uses Project Professional 2013. A senior s...
Question 28: Your company uses Project Professional 2013. You are schedul...
Question 29: You are a project manager who uses Project Professional 2013...
Question 30: You use Project Professional 2013 to manage a project schedu...
Question 31: You are managing a project by using Project Professional 201...
Question 32: You are a project manager in an organization that uses Proje...
Question 33: You are a project manager, and you use Project 2013 for a la...
Question 34: You are a project manager who uses Project Professional 2013...
Question 35: You are a project manager who uses Project Professional 2013...
Question 36: You manage a project and use Project Professional 2013 to tr...
Question 37: You are a Project Manager who uses Project Professional 2013...
Question 38: You are a project manager who uses Project Professional 2013...
Question 39: DRAG DROP Your company uses Project Professional 2013. You a...
Question 40: You manage a project for an organization that relies heavily...
Question 41: Your organization uses Project Professional 2013. A senior s...
Question 42: You are a project manager who uses Microsoft Excel 2013. You...
Question 43: You are a project manager who uses Project Professional 2013...
Question 44: You are an independent project manager who uses Project Prof...
Question 45: Your organization uses Project Professional 2013. You are se...
Question 46: You are a project manager who uses Project Standard 2013. Yo...
Question 47: Your organization uses Project Professional 2013 and records...
Question 48: You are a project manager who uses Project Standard 2013. Yo...
Question 49: Your organization uses Microsoft Project 2013. You are final...
Question 50: You are using Microsoft Project Professional 2013. Three yea...
Question 51: You are a project manager who uses Project Professional 2013...
Question 52: You are a project manager who uses Project Standard 2013. Yo...
Question 53: You are a project manager for a company that is based in New...
Question 54: You are project manager who uses Project Professional 2013. ...
Question 55: You are a project manager who uses Project Professional 2013...
Question 56: Your company uses Project Professional 2013. An organization...
Question 57: You are a project manager, and your organization uses Projec...
Question 58: You are a project manager for a company that uses Project Pr...
Question 59: You are a resource manager who uses Project Standard 2013. Y...
Question 60: You manage a project by using Project Professional 2013. A c...
Question 61: You are a project manager who uses Project Standard 2013. Yo...
Question 62: You are an independent project manager who uses Project Prof...
Question 63: You are a project manager who uses Project Standard 2013. Yo...
Question 64: You are a project manager and have built a project plan by u...
Question 65: You are a project manager, and you successfully complete a s...
Question 66: You are a project manager who uses Project Professional 2013...
Question 67: You are a project manager for a company that uses Project Pr...
Question 68: You use Project Professional 2013 to manage a project that h...
Question 69: DRAG DROP You are an independent project manager who uses Pr...
Question 70: You are a project manager for an organization that uses Proj...
Question 71: You are a project manager who uses Project Professional 2013...
Question 72: You manage a project by using Project Professional 2013. You...
Question 73: You are a project manager who uses Project Professional 2013...
Question 74: DRAG DROP You are a project manager who uses Microsoft Proje...
Question 75: You use Project Professional 2013 to manage a project for yo...
Question 76: You are a project manager who uses Project Professional 2013...
Question 77: You are a project manager for an organization that uses Proj...
Question 78: You are a program manager. Your project managers use Project...
Question 79: You manage a project by using Project Professional 2013. The...
Question 80: You are a project manager who uses Project Professional 2013...
Question 81: You are a project manager who uses Project Standard 2013, an...
Question 82: You are a project manager who uses Project Professional 2013...
Question 83: You are a project manager who uses Project Standard 2013. Yo...
Question 84: Your company uses Project Professional 2013. You are buildin...
Question 85: You are a project manager who uses Project Professional 2013...
Question 86: You are an independent project manager who uses Project Prof...
Question 87: You are a project manager who uses Project Professional 2013...
Question 88: You manage a project by using Project Professional 2013. The...
Question 89: Your company uses Project Professional 2013, and you are set...
Question 90: You are a manager for an organization that uses Project Prof...
Question 91: You are managing a project by using Project Professional 201...
Question 92: Your company uses Project Professional 2013. You are a progr...
Question 93: DRAG DROP You are a senior project manager in a software dev...
Question 94: Your project managers manage several projects using Project ...
Question 95: You are a project manager who uses Project Standard 2013. Yo...
Question 96: You are a program manager for a complex software development...
Question 97: You are a project manager who uses Project Standard 2013. Yo...
Question 98: You manage a project by using Project Standard 2013. You nee...
Question 99: You manage a project schedule by using Project Professional ...
Question 100: While scheduling with Project Professional 2013 you notice t...
Question 101: You are a project manager who uses Project Standard 2013. A ...