Explanation/Reference:
Note:
* You can model these more complex billing schemes by using rate-table features in Project:
1. Right-click the resource, and from the list select Information.
2. On the Resource Information dialog, click the Costs tab.
3. In the Cost rate tables, click the A (Default) tab.
4. In the Effective Date column, enter the date when the rate change takes effect.
5. In the Standard Rate and Overtime Rate columns, type the resource rates.
6. To enter a rate change that takes place on another date, in the additional rows of the cost rate tables, type or select the new date, and the new standard rates and overtime rates.
7. To enter additional sets of pay rates for the same resource, click the B tab, and then repeat steps 3-5.
Reference: Enter costs for resources