You work as a project manager for a construction company that uses Project Professional 2013. You have created your work breakdown structure (WBS) and are adding resources to your tasks. However, one of your tasks requires multiple resources. You have the name of the project's lead support individual, and you have been provided with the equivalent of three full-time support resources. These three resources are not named individuals but are part of a group. The actual individuals from this group will change based on coverage schedules. The resources have the following cost structures: * The lead is billed out at S175/hour. * The group resources are billed out at $140/hour. You need to add these resources to the schedule and track your project costs. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)