Question 98/101

You manage a project by using Project Standard 2013.
You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2.
What should you do?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (101q)
Question 1: You are a senior project manager, and your organization uses...
Question 2: You are a project manager who uses Project Professional 2013...
Question 3: You are a project manager who uses Project Professional 2013...
Question 4: Your company uses Project Professional 2013. You are setting...
Question 5: You are using Project Standard 2013. Management wants to see...
Question 6: DRAG DROP You are a project manager who uses Project Standar...
Question 7: You are a project manager, and your organization uses Projec...
Question 8: Your company uses Project Standard 2013 to track project pro...
Question 9: You work as a project manager for a construction company tha...
Question 10: You manage a project for an organization that uses Project P...
Question 11: You are a project manager for a company that uses baselines ...
Question 12: You are a project manager who uses Project Professional 2013...
Question 13: You are a program manager who uses Project Professional 2013...
Question 14: While creating a schedule with Project Professional 2013, yo...
Question 15: You are a project manager for a software development company...
Question 16: DRAG DROP You are an independent project manager who uses Pr...
Question 17: You are a project manager for a software development company...
Question 18: Your company uses Project Professional 2013. You have two pr...
Question 19: You are managing a project using Project Professional 2013. ...
Question 20: You are a project manager for a large telecommunications com...
Question 21: Your company uses Project Professional 2013. You have severa...
Question 22: You are a project manager, and your company uses Project Pro...
Question 23: Your organization uses Project Professional 2013 and Microso...
Question 24: You are a project manager who uses Project Professional 2013...
Question 25: You are a project manager for an organization that uses Proj...
Question 26: You are using Project Standard 2013. You want the ability to...
Question 27: Your organization uses Project Professional 2013. A senior s...
Question 28: Your company uses Project Professional 2013. You are schedul...
Question 29: You are a project manager who uses Project Professional 2013...
Question 30: You use Project Professional 2013 to manage a project schedu...
Question 31: You are managing a project by using Project Professional 201...
Question 32: You are a project manager in an organization that uses Proje...
Question 33: You are a project manager, and you use Project 2013 for a la...
Question 34: You are a project manager who uses Project Professional 2013...
Question 35: You are a project manager who uses Project Professional 2013...
Question 36: You manage a project and use Project Professional 2013 to tr...
Question 37: You are a Project Manager who uses Project Professional 2013...
Question 38: You are a project manager who uses Project Professional 2013...
Question 39: DRAG DROP Your company uses Project Professional 2013. You a...
Question 40: You manage a project for an organization that relies heavily...
Question 41: Your organization uses Project Professional 2013. A senior s...
Question 42: You are a project manager who uses Microsoft Excel 2013. You...
Question 43: You are a project manager who uses Project Professional 2013...
Question 44: You are an independent project manager who uses Project Prof...
Question 45: Your organization uses Project Professional 2013. You are se...
Question 46: You are a project manager who uses Project Standard 2013. Yo...
Question 47: Your organization uses Project Professional 2013 and records...
Question 48: You are a project manager who uses Project Standard 2013. Yo...
Question 49: Your organization uses Microsoft Project 2013. You are final...
Question 50: You are using Microsoft Project Professional 2013. Three yea...
Question 51: You are a project manager who uses Project Professional 2013...
Question 52: You are a project manager who uses Project Standard 2013. Yo...
Question 53: You are a project manager for a company that is based in New...
Question 54: You are project manager who uses Project Professional 2013. ...
Question 55: You are a project manager who uses Project Professional 2013...
Question 56: Your company uses Project Professional 2013. An organization...
Question 57: You are a project manager, and your organization uses Projec...
Question 58: You are a project manager for a company that uses Project Pr...
Question 59: You are a resource manager who uses Project Standard 2013. Y...
Question 60: You manage a project by using Project Professional 2013. A c...
Question 61: You are a project manager who uses Project Standard 2013. Yo...
Question 62: You are an independent project manager who uses Project Prof...
Question 63: You are a project manager who uses Project Standard 2013. Yo...
Question 64: You are a project manager and have built a project plan by u...
Question 65: You are a project manager, and you successfully complete a s...
Question 66: You are a project manager who uses Project Professional 2013...
Question 67: You are a project manager for a company that uses Project Pr...
Question 68: You use Project Professional 2013 to manage a project that h...
Question 69: DRAG DROP You are an independent project manager who uses Pr...
Question 70: You are a project manager for an organization that uses Proj...
Question 71: You are a project manager who uses Project Professional 2013...
Question 72: You manage a project by using Project Professional 2013. You...
Question 73: You are a project manager who uses Project Professional 2013...
Question 74: DRAG DROP You are a project manager who uses Microsoft Proje...
Question 75: You use Project Professional 2013 to manage a project for yo...
Question 76: You are a project manager who uses Project Professional 2013...
Question 77: You are a project manager for an organization that uses Proj...
Question 78: You are a program manager. Your project managers use Project...
Question 79: You manage a project by using Project Professional 2013. The...
Question 80: You are a project manager who uses Project Professional 2013...
Question 81: You are a project manager who uses Project Standard 2013, an...
Question 82: You are a project manager who uses Project Professional 2013...
Question 83: You are a project manager who uses Project Standard 2013. Yo...
Question 84: Your company uses Project Professional 2013. You are buildin...
Question 85: You are a project manager who uses Project Professional 2013...
Question 86: You are an independent project manager who uses Project Prof...
Question 87: You are a project manager who uses Project Professional 2013...
Question 88: You manage a project by using Project Professional 2013. The...
Question 89: Your company uses Project Professional 2013, and you are set...
Question 90: You are a manager for an organization that uses Project Prof...
Question 91: You are managing a project by using Project Professional 201...
Question 92: Your company uses Project Professional 2013. You are a progr...
Question 93: DRAG DROP You are a senior project manager in a software dev...
Question 94: Your project managers manage several projects using Project ...
Question 95: You are a project manager who uses Project Standard 2013. Yo...
Question 96: You are a program manager for a complex software development...
Question 97: You are a project manager who uses Project Standard 2013. Yo...
Question 98: You manage a project by using Project Standard 2013. You nee...
Question 99: You manage a project schedule by using Project Professional ...
Question 100: While scheduling with Project Professional 2013 you notice t...
Question 101: You are a project manager who uses Project Standard 2013. A ...