You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.
You have the following requirements:
All work and progress on individual projects must be reflected in the e-commerce portal development

program.
Each group must be able to manage their own tasks.

You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.
Where should you add resources?