DRAG DROP
You are an administrator for your company's Microsoft PPM environment. You implement several project level enterprise custom fields and add these fields to new and existing views.
Some users report they spend too much time scrolling left and right in a view named Team Status. You determine that the column width for the Enterprise Project Type field may be causing the issue.
You need to reduce the amount of scrolling.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place: