You are a project manager for an organization that uses Microsoft PPM. You plan each project in phases. Team members must only see the assignments from a selected phase. All reports and project schedule views must reflect the entire project schedule, so the entire project is visible to the management team. You need to configure Microsoft PPM. What should you do?