HOTSPOT
You are the project manager for a real estate management company. You are using Microsoft Project to manage the development of a new restaurant. The schedule includes a task named Equipment delivery.
Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9,
2016.
You need to modify the Equipment delivery task.
How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.
Hot Area: