DRAG DROP
You are a program manager who is using Microsoft PPM and Microsoft Project to manage an e-commerce portal development program.
The program is separated into individual projects that represent each area of development, so that each group can manage its own tasks while still having progress visibility at the program level.
You need to be able to manage the overall program as well as its associated individual projects within Project Center. This includes the project sites associated with both the program and the individual projects.
Each individual project site should be a subsite of the overall program project site.
You need to create the master program, the individual projects, and their associated project sites.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
Select and Place: