Topic 7, Scenario 7 "Test Estimation"
You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on.
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (35q)
Question 1: Topic 10, Scenario 10, V1 "Online Application" There is a fo...
Question 2: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 3: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 4: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 5: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 6: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 7: Topic 8, Scenario 8, V2 "Test Proems Improvement' You have r...
Question 8: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 9: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 10: Topic 7, Scenario 7 "Test Estimation" You have been contract...
Question 11: Topic 6, Scenario 6, V3 "Independent Test Team" Three exit c...
Question 12: Topic 5, Scenario 5, V2 "Human Resource System" For the firs...
Question 13: Topic 10, Scenario 10, V1 "Online Application" There is a fo...
Question 14: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 15: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 16: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 17: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 18: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 19: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 20: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 21: Topic 5, Scenario 5, V2 "Human Resource System" For the firs...
Question 22: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 23: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 24: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 25: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 26: Topic 11, Scenario 11 "Incident Management" The following is...
Question 27: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 28: Topic 8, Scenario 8, V2 "Test Proems Improvement' You have r...
Question 29: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 30: Topic 6, Scenario 6, V4 "Independent Test Team" You have for...
Question 31: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 32: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 33: Topic 12, Scenario 12 "Automatic Teller Machine (ATM)" You a...
Question 34: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 35: Topic 10, Scenario 10, V3 "Online Application" The cancellat...