Question 24/35

Topic 4, Scenario 4, V2 "Test Management Tool"
The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.
Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (35q)
Question 1: Topic 10, Scenario 10, V1 "Online Application" There is a fo...
Question 2: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 3: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 4: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 5: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 6: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 7: Topic 8, Scenario 8, V2 "Test Proems Improvement' You have r...
Question 8: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 9: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 10: Topic 7, Scenario 7 "Test Estimation" You have been contract...
Question 11: Topic 6, Scenario 6, V3 "Independent Test Team" Three exit c...
Question 12: Topic 5, Scenario 5, V2 "Human Resource System" For the firs...
Question 13: Topic 10, Scenario 10, V1 "Online Application" There is a fo...
Question 14: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 15: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 16: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 17: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 18: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 19: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 20: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 21: Topic 5, Scenario 5, V2 "Human Resource System" For the firs...
Question 22: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 23: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 24: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 25: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 26: Topic 11, Scenario 11 "Incident Management" The following is...
Question 27: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 28: Topic 8, Scenario 8, V2 "Test Proems Improvement' You have r...
Question 29: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 30: Topic 6, Scenario 6, V4 "Independent Test Team" You have for...
Question 31: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 32: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 33: Topic 12, Scenario 12 "Automatic Teller Machine (ATM)" You a...
Question 34: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 35: Topic 10, Scenario 10, V3 "Online Application" The cancellat...