The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.
Which test management control option is most appropriate to adopt under these circumstances?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (35q)
Question 1: Topic 10, Scenario 10, V1 "Online Application" There is a fo...
Question 2: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 3: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 4: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 5: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 6: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 7: Topic 8, Scenario 8, V2 "Test Proems Improvement' You have r...
Question 8: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 9: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 10: Topic 7, Scenario 7 "Test Estimation" You have been contract...
Question 11: Topic 6, Scenario 6, V3 "Independent Test Team" Three exit c...
Question 12: Topic 5, Scenario 5, V2 "Human Resource System" For the firs...
Question 13: Topic 10, Scenario 10, V1 "Online Application" There is a fo...
Question 14: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 15: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 16: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 17: Topic 6, Scenario 6, V2 "Independent Test Team" The project ...
Question 18: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 19: Topic 4, Scenario 4, V1 "Test Management Tool" A software de...
Question 20: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 21: Topic 5, Scenario 5, V2 "Human Resource System" For the firs...
Question 22: Topic 5, Scenario 5, V1"Human Resource System" You have rece...
Question 23: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 24: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 25: Topic 4, Scenario 4, V2 "Test Management Tool" The project s...
Question 26: Topic 11, Scenario 11 "Incident Management" The following is...
Question 27: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 28: Topic 8, Scenario 8, V2 "Test Proems Improvement' You have r...
Question 29: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 30: Topic 6, Scenario 6, V4 "Independent Test Team" You have for...
Question 31: Topic 6, Scenario 6, V1 "Independent Test Team" XYZ is a Swe...
Question 32: Topic 9, Scenario 9 "Test Management Documentation" A softwa...
Question 33: Topic 12, Scenario 12 "Automatic Teller Machine (ATM)" You a...
Question 34: Topic 10, Scenario 10, V3 "Online Application" The cancellat...
Question 35: Topic 10, Scenario 10, V3 "Online Application" The cancellat...