Valid INTE Dumps shared by ExamDiscuss.com for Helping Passing INTE Exam! ExamDiscuss.com now offer the newest INTE exam dumps, the ExamDiscuss.com INTE exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com INTE dumps with Test Engine here:
A firm completes its near level production, five-month demand plan for the next business planning cycle: Month 1Month 2Month 3Month 4Month 5 Demand Forecast15,00020,00025,00025,00018,000 Production Plan (Regular Time)20,00020,00020,00020,00018,000 Production Plan (Overtime)5,000 Ending Inventory5,0005,000 Average Inventory2,5005,0002,500 Workforce PlanningStarting WorkforceMonth 1Month 2Month 3Month 4Month 5 Hires7 Layoffs2 Actual Workforce Size132020202018 Regular Time Hours Required2,0002,0002,0002,0001,800 Overtime Hours Required500 Costs Regular time cost per unit$15 Overtime cost per unitS25 Monthly inventory cost per unit$1 Cost of hire$1,500 Cost of layoffS400 What is the cost of this demand plan?
Correct Answer: C
The total cost is calculated by summing the costs of regular and overtime production, hiring, layoffs, and inventory. Calculations consider each month's figures and associated costs, providing a comprehensive total that aligns with supply chain cost management principles.