Your project team has completed the quantitative risk analysis for your project work. Based on their findings, they need to update the risk register with several pieces of information. Which one of the following components is likely to be updated in the risk register based on their analysis?
Correct Answer: C
Section: Volume A Explanation: The outcome of quantitative analysis can create a listing of prioritized risks that should be updated in the risk register. The project team will create and update the risk register with four key components: * probabilistic analysis of the project * probability of achieving time and cost objectives * list of quantified risks * trends in quantitative risk analysis Incorrect Answers: A, B, D: These subjects are not updated in the risk register as a result of quantitative risk analysis.