Which of the following processes addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and activities into the budget?
Correct Answer: B
is incorrect. Qualitative analysis is the definition of risk factors in terms of high/medium/low or a numeric scale (1 to 10). Hence it determines the nature of risk on a relative scale. Some of the qualitative methods of risk analysis are: Scenario analysis- This is a forward-looking process that can reflect risk for a given point in time. Risk Control Self -assessment (RCSA) - RCSA is used by enterprises (like banks) for the identification and evaluation of operational risk exposure. It is a logical first step and assumes that business owners and managers are closest to the issues and have the most expertise as to the source of the risk. RCSA is a constructive process in compelling business owners to contemplate, and then explain, the issues at hand with the added benefit of increasing their accountability.