You are preparing to complete the quantitative risk analysis process with your project team and several subject matter experts. You gather the necessary inputs including the project's cost management plan. Why is it necessary to include the project's cost management plan in the preparation for the quantitative risk analysis process?
Correct Answer: A
is incorrect. This is not a valid statement. The cost management plan is an input to the quantitative risk analysis process. Answer:B is incorrect. The cost management plan defines the estimating, budgeting, and control of the project's cost. Answer:C is incorrect. While the cost management plan does define the cost change control system, this is not the best answer for this