Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:
You are the project manager of GRT project. You discovered that by bringing on more qualified resources or by providing even better quality than originally planned, could result in reducing the amount of time required to complete the project. If your organization seizes this opportunity it would be an example of what risk response?
Correct Answer: B
is incorrect. - The share strategy is similar as transfer because in this a portion of the risk is shared with an external organization or another internal entity. Answer:A is incorrect. The enhance strategy closely watches the probability or impact of the risk event to assure that the organization realizes the benefits. The primary point of this strategy is to attempt to increase the probability and/or impact of positiveAnswer:C is incorrect. Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs.