Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?
Correct Answer: D
Explanation/Reference: Explanation: Risk management is an ongoing project activity. It should be an agenda item at every project status meeting. Incorrect Answers: A: Risk management happens throughout the project as does project planning. B: Milestones are good times to do reviews, but risk management should happen frequently. C: This answer would only be correct if the project has a status meeting just once per month in the project.