Which method in Schedule and Budget Compression looks at your tasks and sees if any of them can be overlapped.
Correct Answer: A
Fast-Tracking is a schedule compression technique where tasks that are normally done in sequence are performed in parallel for at least a portion of their duration. This method is used when time is a higher priority than cost and can be applied when activities can be overlapped without significantly increasing the risk of the project. It's important to note that while fast-tracking can reduce the project timeline, it may also increase risk and requires careful coordination. References: The concept of Fast-Tracking is discussed in the context of schedule compression techniques in project management literature and aligns with the PMBOK Guide standards, which serve as a foundational reference for project management practices123.