Valid PK0-005 Dumps shared by ExamDiscuss.com for Helping Passing PK0-005 Exam! ExamDiscuss.com now offer the newest PK0-005 exam dumps, the ExamDiscuss.com PK0-005 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-005 dumps with Test Engine here:
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
Correct Answer: A
A rollback plan is used when an issue is identified during testing or implementation. It allows the team to revert to the previous state, removing the new package. This aligns with CompTIA Project+ guidance on implementing fallback strategies for risk management.