A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
Correct Answer: B
Escalating to the Change Control Board (CCB) is necessary when a change request impacts the project's timeline or budget. The CCB reviews and approves changes, ensuring that they align with project objectives. CompTIA Project+ highlights the role of the CCB in change management processes.