A project manager provided details regarding the completion of the following tasks: Equipment procurement took less time than estimated. Equipment installation went according to schedule. Which of the following should the project manager update?
Correct Answer: B
The Project Gantt chart is a scheduling tool used to track task progress and timelines. When tasks are completed ahead of schedule, updating the Gantt chart ensures accurate tracking. This aligns with CompTIA Project+ recommendations on project scheduling and monitoring.