Question 41/140

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (140q)
Question 1: A customer requests some changes to a product, and those cha...
Question 2: An organization was fined due to an audit finding that revea...
Question 3: A project manager has received different functional requests...
Question 4: During a status meeting for a multisystem program, a program...
Question 5: Which of the following should be considered first when deter...
Question 6: Defects associated with project deliverables have been repor...
Question 7: A PM needs to calculate the progress of the whole project sc...
Question 8: A business analyst has gathered information directly from th...
Question 9: Project team members are leaving the company due to a stress...
Question 10: A PM is working with stakeholders in the discovery phase and...
Question 11: Which of the following activities are performed during the c...
Question 12: Which of the following contract types in project procurement...
Question 13: After months of recruiting, a team finally found the right c...
Question 14: A visual that displays team progress was created for stand-u...
Question 15: Given the following velocity chart: (Exhibit) Which of the f...
Question 16: During a staff meeting, a project manager voices a concern a...
Question 17: A project team is working on a document to precisely describ...
Question 18: A project manager provided details regarding the completion ...
Question 19: Following the approval of a change by the CCB, which of the ...
Question 20: During a quality analysis review, the causes of several issu...
Question 21: Which of the following best describes a manufacturer's oblig...
Question 22: One of the key steps in controlling changes lo software is o...
Question 23: Given the following network diagram: Which of the following ...
Question 24: A project manager is currently meeting with a vendor who com...
Question 25: Given the following information: (Exhibit) Which of the foll...
Question 26: Which of the following BEST identifies the intent and purpos...
Question 27: A development team, which is working on a software project d...
Question 28: A new project team started work three months ago. The team m...
Question 29: A project manager distributes minutes after each project mee...
Question 30: A key stakeholder recommends to a senior developer that a ne...
Question 31: Project stakeholders have asked the team to use Scrum to run...
Question 32: Although a project was successfully released into production...
Question 33: A team member identifies a critical issue in production. Whi...
Question 34: During timeline creation, the project manager is unsure if t...
Question 35: A PM is responsible for implementing a new customer relation...
Question 36: Which of the following would most likely take place when a t...
Question 37: A project is running over budget, and due to new legislation...
Question 38: Several stakeholders have declined the invitation for the ki...
Question 39: During the project initiation phase, a project manager needs...
Question 40: A project manager needs to update the project sponsor and se...
Question 41: A few weeks before a project is scheduled to be completed, t...
Question 42: Which of the following should occur when implementing an IT ...
Question 43: A vendor manager communicates to the project manager that a ...
Question 44: A project is moving into the user acceptance testing phase. ...
Question 45: Which of the following is a consideration when determining a...
Question 46: A new project has been assigned to a project manager. In ord...
1 commentQuestion 47: During the execution phase of a project, the project team fa...
Question 48: A project manager has been assigned to a new project. During...
Question 49: Which of the following are primary features provided by a st...
Question 50: Two stakeholders, who have a history of animosity toward one...
Question 51: Which of the following cloud models is designed to provide c...
Question 52: Which of the following can a project manager infer from the ...
Question 53: A PM is working to establish accepted communication channels...
Question 54: Two developers are discussing the design solution for a part...
Question 55: A risk management team for a software project decided to out...
Question 56: An institution wants to implement software solutions to help...
Question 57: Before a configuration can be made to a system in developmen...
Question 58: An IT infrastructure change request needs to be implemented ...
Question 59: After new capabilities were deployed in a system, issues wit...
Question 60: A car manufacturer is presenting to three vendors the abilit...
Question 61: A financial manager reports that several employees' allocati...
Question 62: Which of the following requires the MOST availability from t...
Question 63: A team is analyzing the backlog in order to decide what to i...
Question 64: SIMULATION During a gate review meeting, the deliverable was...
Question 65: Which of the following tools is best to use when conducting ...
Question 66: A project team gathers weekly to review its progress. Which ...
Question 67: A project team needs to understand what needs to be done, wh...
Question 68: As part of the planning phase, a PM has defined tasks, durat...
Question 69: During a brainstorming meeting, a project manager identifies...
Question 70: During the progress of a project, the stakeholders require t...
Question 71: A PM is working on the schedule for a project that has techn...
Question 72: A project manager is receiving reports of the actual project...
Question 73: A project team is defining operational training, discussing ...
Question 74: During the execution phase of a project, team members have b...
Question 75: Which of the following statements best describes zero-based ...
Question 76: A project was closed according to the planned project schedu...
Question 77: A project manager is assigned to a multinational project wit...
Question 78: A project manager, who finished a project some time ago, kee...
Question 79: A project manager realizes that a project will not be comple...
Question 80: Which of the following tools should a project manager use to...
Question 81: A project team is working remotely from different locations ...
Question 82: A project manager is beginning a new project that will inclu...
Question 83: Following a successful release, a project manager sent a sur...
Question 84: A project manager and team are reviewing a task that is supp...
Question 85: A project manager is coordinating multiple teams of six peop...
Question 86: After a release, the project sponsor received an escalation ...
Question 87:
Question 88: A project manager will conduct a release on the third Friday...
Question 89: To gather requirements from stakeholders, the project manage...
Question 90: Which of the following activities would a project manager pe...
Question 91: A company needs to have structured cabling installed in one ...
Question 92: A project team member wrote a user guide over the past ten d...
Question 93: During a code implementation, a senior developer and junior ...
Question 94: A project manager is monitoring team performance by comparin...
Question 95: A project team needs a tool to store information that is cap...
Question 96: A project manager queries stakeholders to identify the right...
Question 97: A company that is implementing an updated version of its mai...
Question 98: By developing a project schedule, a PM has already validated...
Question 99: When assigning access, classifying information based on sens...
Question 100: A project manager reports that the implementation of a new s...
Question 101: A team currently has a schedule for each sprint that changes...
Question 102: Halfway through a project, the sponsor states that the proje...
Question 103: Which of the following pieces of data are examples of Pll?...
Question 104: After determining the appropriate maintenance window, which ...
Question 105: Which of the following should be the PRIMARY basis for estab...
Question 106: Which of the following is the most important activity for th...
Question 107: A stakeholder raises a concern with a project manager becaus...
Question 108: A meeting agenda included the following items: . Review the ...
Question 109: Which of the following would be MOST beneficial to do before...
Question 110: During the testing phase of a project, the legal department ...
Question 111: Which of the following items must be protected as Pll? (Sele...
Question 112: During a brainstorming session, a team member expressed conc...
Question 113: Which of the following tools is best to use for storing less...
Question 114: Which of the following activities would force a team to remo...
Question 115: Which of the following describes three-tier architecture?...
Question 116: A procurement team analyzes solutions submitted from multipl...
Question 117: Which of the following would be the most helpful in providin...
Question 118: A contractor attended a project meeting that was exclusively...
Question 119: An existing application that is highly utilized by clients i...
Question 120: As a result of lessons learned, a project manager convenes a...
Question 121: A project manager is assigned an initiative in a highly regu...
Question 122: Which of the following is required to provide a hardware ins...
Question 123: A global franchise requests that a company provide a solutio...
Question 124: Which of the following artifacts should project team members...
Question 125: A project team participates in a brainstorming session to de...
Question 126: A global franchise requests that a company provide a solutio...
Question 127: A project manager wants to be confident that the most crucia...
Question 128: A project manager has been informed that the delivery of req...
Question 129: Which of the following is a capital expense?...
Question 130: A new junior PM who has ownership of a project does not unde...
Question 131: When introducing a new information asset, what is the MOST i...
Question 132: The quarterly financial report displays losses from a projec...
Question 133: A project manager needs to ensure that the products produced...
Question 134: Due to budgetary and time constraints, a PM scheduled a meet...
Question 135: After a product is released for production, a tester perform...
Question 136: When creating a project schedule, a project manager adds act...
Question 137: A client made a change request. Implementing the change will...
Question 138: A sponsor prefers to communicate with the team using email, ...
Question 139: Which of the following is a typical characteristic of Scrum?...
Question 140: Hackers are attempting to extract large amounts of data to s...