Valid PK0-005 Dumps shared by ExamDiscuss.com for Helping Passing PK0-005 Exam! ExamDiscuss.com now offer the newest PK0-005 exam dumps, the ExamDiscuss.com PK0-005 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-005 dumps with Test Engine here:
A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?
Correct Answer: B
Smoke testing is a preliminary test to check whether the most essential functions of the software work correctly. It is often the first step in the testing phase and helps confirm that the build is stable enough for further testing. This aligns with CompTIA Project+ practices for software testing phases.