A public agency opens a tendering process for a road building project that lasts approximately 1 year. They post theirrequirements on public journal and receive some interests. After conducting due diligence process and selecting the lowest bidder, the project commences. However, the supplier complains that price of material increases because of a shortage of supply, thenthey demands an 5% uptick in contract value. The agency investigates the increment and sees that there is indeed a fluctuation in prices of supplier's input. They are likely to accept the proposal, but they are also concerned that supplier may demand more. To avoid making another concession with the supplier, which of the following should be a priority action of the agency?
Correct Answer: C
Explanation The agency (buyer) has made a concession about the price. Possibly the supplier will request another concession (the salami tactics). To avoid this to be happened, the agency should only allow a concession as an exception, make sure that the concession is documented and only permitted against some exceptional circumstances, and seek agreement to this from the supplier. LO 3, AC 3.2