Valid AD0-E318 Dumps shared by ExamDiscuss.com for Helping Passing AD0-E318 Exam! ExamDiscuss.com now offer the newest AD0-E318 exam dumps, the ExamDiscuss.com AD0-E318 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AD0-E318 dumps with Test Engine here:
A project Manager is setting up a Gantt chart for a new project implementation. The company Is using a Hybrid deployment model, will interact with several systems, and be heavily customized to fit the customer needs. The PMO not know the Adobe Campaign project phase and wants to make sure important tasks are not missed, The initiated list of Go-Live activities is as follow: Migrate appropriate objects from Stage to Production Make sure Production SFTP is created Validate that import/export workflow work as expected Make sure the Workflow Supervisor group is assigned to the appropriate workflows What else should the Architect do before the Go-live?
Correct Answer: A
The best option before the Go-live is to create a RunBook and perform a Customer Care handoff. This will ensure that the customer knows how to operate and maintain the Adobe Campaign instance after the go-live. This is important to ensure the smooth operation of the Adobe Campaign instance and to ensure that the customer can use all the features and capabilities of the Adobe Campaign instance effectively.