Valid APM-PMQ Dumps shared by ExamDiscuss.com for Helping Passing APM-PMQ Exam! ExamDiscuss.com now offer the newest APM-PMQ exam dumps, the ExamDiscuss.com APM-PMQ exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com APM-PMQ dumps with Test Engine here:
You are in the design phase of a project to deliver offices on a newly acquired plot of land. You have now completed extra surveys and discovered that the ground conditions are a lot softer than expected, meaning the design and delivery will be far more complex and costly. You did not account for this in your risk register. Which of the following statements about the project business case is true?