Valid APM-PMQ Dumps shared by ExamDiscuss.com for Helping Passing APM-PMQ Exam! ExamDiscuss.com now offer the newest APM-PMQ exam dumps, the ExamDiscuss.com APM-PMQ exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com APM-PMQ dumps with Test Engine here:
Which of the following are not typical responses to risks? * Complete root cause analysis to understand why the situation has occurred. * Reduce the probability of the threat occurring or the impact on the project. * Change objectives or practices to change the cause of the threat so it can no longer occur. * There are no acceptable or viable approaches to take to avoid or reduce, so the threat and any residual risk must be managed. * Prepare a risk management plan to document the risk and give it to your sponsor. * Pass the responsibility for bearing the impact of the threat from one party to another.
Correct Answer: B
Detailed Explanation: * Preparing a risk management plan (5) is part of risk planning, not a direct response to risks.