During a project review, which of the following would be the best indicator of how the project outputs are progressing?
Correct Answer: A
Detailed Explanation: * Earned Value:This is a key performance indicator (KPI) in project management that integrates cost, scope, and schedule. It provides a clear view of how much progress has been made against the work planned and money spent. * Unsuitable Options: * B: Benefits realization assesses post-project success, not ongoing progress. * C: Resource management is unrelated to deliverables progress. * D: Budget tracking only measures financial health without linking to project outputs.