Valid SAFe-RTE Dumps shared by ExamDiscuss.com for Helping Passing SAFe-RTE Exam! ExamDiscuss.com now offer the newest SAFe-RTE exam dumps, the ExamDiscuss.com SAFe-RTE exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com SAFe-RTE dumps with Test Engine here:
Which two actions must the Release Train Engineer (RTE) take when facilitating the Pro-gram Increment (PI) Planning event? (Choose two.)
Correct Answer: B,D
Program risks can be categorized based on whether they are Deferred or Owned. A deferred risk is one that has been identified but is not being actively addressed at the moment, possibly due to prioritization of other risks or resource constraints. An owned risk is one that has been assigned to an individual or team who is responsible for managing and mitigating the risk. This categorization helps in tracking and accountability within the SAFe framework.