Correct Answer: B,D
The outputs of Iteration Planning within the SAFe framework are crucial for guiding the work of Agile teams during an iteration. Two primary outputs of this process are:
* Iteration Goals: These are the objectives that the team commits to achieving during the iteration. They provide a clear direction and purpose for the iteration, aligning the team's efforts with the larger goals of the Agile Release Train (ART).
* Iteration Backlog: This is the set of stories, including enablers, that the team plans to deliver by the end of the iteration. Each item in the iteration backlog has defined acceptance criteria and an estimate, which are recorded in the team backlog.
Together, these outputs ensure that the team has a clear understanding of what needs to be accomplished and the work items that they have committed to delivering. This alignment is essential for maintaining the flow of value through the ART and achieving the broader objectives of the program increment (PI)1.