Valid SAFe-RTE Dumps shared by ExamDiscuss.com for Helping Passing SAFe-RTE Exam! ExamDiscuss.com now offer the newest SAFe-RTE exam dumps, the ExamDiscuss.com SAFe-RTE exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com SAFe-RTE dumps with Test Engine here:
What is the best way for the Release Train Engineer to show progress of work in the cur-rent Program Increment (PI) to management?
Correct Answer: A
The best way for a Release Train Engineer (RTE) to show progress of work in the current Program Increment (PI) to management is to conduct a System Demo. This is supported by the SAFe documentation which states that the System Demo is an integral part of the PI, providing an opportunity to inspect and adapt the solutions being developed1. It serves as a platform to showcase the achievements of the Agile Release Train (ART) and allows stakeholders to provide feedback1. This event aligns with the principle of transparency and provides a clear, objective measure of progress1.