Valid Certified-Business-Analyst Dumps shared by ExamDiscuss.com for Helping Passing Certified-Business-Analyst Exam! ExamDiscuss.com now offer the newest Certified-Business-Analyst exam dumps, the ExamDiscuss.com Certified-Business-Analyst exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com Certified-Business-Analyst dumps with Test Engine here:
Universal Containers uses Kanban to complete its Salesforce development. In the middle of a sprint, the sales manager submits an important item to the team. What should the business analyst do next?
Correct Answer: A
The business analyst should ask the team to reprioritize the backlog and work on the item at the top. This is because Kanban is a development model that focuses on continuous delivery and flow of work, rather than fixed iterations or sprints. Kanban uses a visual board that shows the status of work items across different stages, such as backlog, in progress, done, etc. Work items are pulled from one stage to another when there is available capacity or demand, rather than according to a predefined schedule or plan. Reprioritizing the backlog can help the team accommodate the new item and ensure that the most important or urgent work is done first. Asking the team to commit to the work for the next sprint may not be a good option because Kanban does not use sprints or time-boxed iterations. Asking the team to pivot and complete the work immediately may not be a good option because it may disrupt the flow of work or create bottlenecks or waste in Kanban. References: https://trailhead.salesforce.com/content/learn/modules/salesforce-business-analyst-certification-prep/user-accepta https://trailhead.salesforce.com/en/content/learn/modules/agile-development-with-scrum