Valid C_TS422_2023 Dumps shared by ExamDiscuss.com for Helping Passing C_TS422_2023 Exam! ExamDiscuss.com now offer the newest C_TS422_2023 exam dumps, the ExamDiscuss.com C_TS422_2023 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS422_2023 dumps with Test Engine here:
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
Correct Answer: B
You can achieve planning only for specific resources in Advanced Planning (PP/DS) by using a resource group. A resource group is a collection of resources that share the same characteristics and can be used interchangeably for production. You can assign a resource group to a product or a production version, and then use the resource group as a selection criterion in the planning board or the product view. This way, you can restrict the planning to only those resources that belong to the resource group. Reference: SAP S/4HANA Manufacturing for Planning & Scheduling - Implementation Guide, page 25; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 79.