Valid C_TS422_2023 Dumps shared by ExamDiscuss.com for Helping Passing C_TS422_2023 Exam! ExamDiscuss.com now offer the newest C_TS422_2023 exam dumps, the ExamDiscuss.com C_TS422_2023 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS422_2023 dumps with Test Engine here:
If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?
Correct Answer: C
In reorder point planning, the system compares the available stock with the reorder point to determine the net requirements. If the available stock falls below the reorder point, the system triggers a procurement proposal for the material. The quantity of the procurement proposal depends on the lot size procedure that is defined in the material master. The lot size procedure determines how the system calculates the order quantity based on factors such as demand, costs, and storage space. There are different types of lot size procedures, such as static, periodic, or optimum lot size. Reference: [Production Planning with SAP S/4HANA], page 156; [SAP Help Portal: Lot Size Calculation].