Valid C_TS422_2023 Dumps shared by ExamDiscuss.com for Helping Passing C_TS422_2023 Exam! ExamDiscuss.com now offer the newest C_TS422_2023 exam dumps, the ExamDiscuss.com C_TS422_2023 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS422_2023 dumps with Test Engine here:
In documentation for MRP in Advanced Planning, you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?
Correct Answer: C
Infinite planning is a method of material requirements planning (MRP) that creates new orders without checking the capacity availability of the work centers. This means that the capacity requirements of a new order are created regardless of the existing capacity load or constraints of the work center. Infinite planning assumes that the required capacity can be increased or adjusted as needed. Infinite planning is suitable for situations where the capacity supply is flexible and the demand is urgent or unpredictable. However, infinite planning can also result in capacity overloads or unrealistic schedules that need to be resolved later by capacity leveling or rescheduling. Reference: SAP S/4HANA Production Planning and Manufacturing II, Unit 1: Material Requirements Planning; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 77.