Which dynamic modification levels can be set in the inspection plan? Note: There are 3 correct answers to this question.
Correct Answer: A,C,D
Dynamic modification levels in SAP QM determine the granularity at which inspection scope changes (e.g., reduced to full inspection) are applied in an inspection plan (transaction QP01):
* Characteristic Level (A): Modification can occur at the individual characteristic level within an operation, allowing specific MICs to skip or intensify based on their quality history.
* Inspection Lot Level (C): The entire inspection lot can be modified (e.g., skipped), based on the quality level for the material or combination (e.g., material/supplier).
* Operation Level (D): Modification can apply to an operation, adjusting all characteristics within it based on performance (e.g., operation-specific skip).
* Inspection Type Level (B): Inspection types define the process (e.g., 01 for GR), but dynamic modification is not set at this level; it's tied to plans or lots.
* Work Center (E): Work centers are execution locations, not a level for dynamic modification in QM.
Thus, "Characteristic level," "Inspection lot level," and "Operation level" are the correct answers.References:
SAP Help Portal - "Dynamic Modification in Inspection Planning"; SAP S/4HANA QM Customizing Guide -
"Dynamic Modification".