Valid PRINCE2-Foundation Dumps shared by ExamDiscuss.com for Helping Passing PRINCE2-Foundation Exam! ExamDiscuss.com now offer the newest PRINCE2-Foundation exam dumps, the ExamDiscuss.com PRINCE2-Foundation exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PRINCE2-Foundation dumps with Test Engine here:
Access PRINCE2-Foundation Dumps Premium Version
(474 Q&As Dumps, 35%OFF Special Discount Code: freecram)
Enter your email address to download PRINCE2.PRINCE2-Foundation.v2023-07-03.q342.pdf
Recent Comments (The most recent comments are at the top.)
Correct answer should be D:
To be following PRINCE2, a project must, as a minimum:
•define its change control approach. This approach must minimally cover:
•how issues are identified and managed
•assessing whether identified issues might have a material impact on the business justification of the project (PRINCE2’s continued business justification principle)
•the roles and responsibilities for change control (PRINCE2’s defined roles and responsibilities principle), including a defined change authority