Valid PRINCE2-Foundation Dumps shared by ExamDiscuss.com for Helping Passing PRINCE2-Foundation Exam! ExamDiscuss.com now offer the newest PRINCE2-Foundation exam dumps, the ExamDiscuss.com PRINCE2-Foundation exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PRINCE2-Foundation dumps with Test Engine here:
Access PRINCE2-Foundation Dumps Premium Version
(474 Q&As Dumps, 35%OFF Special Discount Code: freecram)
Enter your email address to download PRINCE2.PRINCE2-Foundation.v2023-07-03.q342.pdf
Recent Comments (The most recent comments are at the top.)
Correct answer is B: PID:
The project manager is responsible for identifying and documenting the level of tailoring for the project. Tailoring affects how a project is managed and so it is documented as part of the PID, which is reviewed by the appropriate stakeholders and approved by the project board.