During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk. What should the risk manager document as the risk trigger?
Correct Answer: C
A risk trigger is a specific event or condition that signals that a risk is about to occur or has occurred. PMBOK Guide clarifies: " Risk triggers (sometimes called warning signs) are indicators or symptoms that a risk event is about to occur. The risk register should include identified triggers for each risk. " - PMBOK Guide, 6th Edition, Section 11.2.3.1 Thus, documenting the specific event or condition (such as the supplier missing a delivery deadline) is the correct approach. References: PMBOK Guide, 6th Edition, Section 11.2.3.1 Practice Standard for Project Risk Management, PMI, Section 5.3