A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project. What should the risk manager do to prevent this from happening again?
Correct Answer: C
Assigning a risk owner is a foundational principle in risk management, ensuring that each risk has someone fully accountable for monitoring, controlling, and responding to the risk. According to the PMBOK Guide: " Risk owners should be assigned to each risk. The risk owner is the person responsible for planning an appropriate risk response and ensuring it is implemented as planned. " - PMBOK Guide, 6th Edition, Section 11.3.2.1 Without a clearly assigned risk owner, responsibility can be ambiguous, leading to gaps in monitoring and response. References: PMBOK Guide, 6th Edition, Section 11.3.2.1 Practice Standard for Project Risk Management, PMI, Section 5.3