<< Prev Question Next Question >>

Question 3/123

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource ' s availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave.
The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.
What should the risk manager do next?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (123q)
Question 1: A new vice president in one of its divisions observed that t...
Question 2: The major investor in a road construction project is constan...
Question 3: An experienced and the only developer on a software implemen...
Question 4: During a project ' s planning phase, the project team identi...
Question 5: An IT project is 40% complete. During the initial analysis, ...
Question 6: The risk manager notices that in their workshops, most of th...
Question 7: After presenting a list of risks to the major project stakeh...
Question 8: One project in a program needs to be completed in 6 months b...
Question 9: A project team is leading a software development project. Du...
Question 10: Project stakeholders can often be risk averse with little to...
Question 11: A project manager is trying to realize benefits from new mat...
Question 12: A project is at the final development stage. The test lead i...
Question 13: During the project ' s lifecycle, project risk managers must...
Question 14: A major data center initiative involves performing a sensiti...
Question 15: A risk manager monitors risks on a medium-sized project by c...
Question 16: A risk manager has a well-structured risk management process...
Question 17: An organization that spans across different countries underg...
Question 18: During the monthly executive review meeting, the project spo...
Question 19: A risk manager reviews a Monte Carlo schedule risk analysis ...
Question 20: During a project team meeting, a risk manager realizes that ...
Question 21: A risk management professional is currently facilitating the...
Question 22: When conducting a risk identification exercise, what two act...
Question 23: A company manages confidential customer information, and a d...
Question 24: While developing a risk management plan for a complex progra...
Question 25: A risk manager is working on the risk management plan for a ...
Question 26: A risk manager is conducting a qualitative risk analysis for...
Question 27: In a project to promote public health and mitigate health ri...
Question 28: A project manager has finished the project charter for a pro...
Question 29: A financial service firm adheres to heavily regulated compli...
Question 30: Some issues and unexpected results were found after completi...
Question 31: During project execution, a project manager invites the stak...
Question 32: A project manager is developing the risk register and works ...
Question 33: A certain risk is identified for a major project, and the ri...
Question 34: A project has a S0S4 chance of a US$100 000 profit and a 40%...
Question 35: A project is in the execution phase and involves large volum...
Question 36: A risk manager was recently hired to assist with a mid-sized...
Question 37: A risk manager manages risks in a construction project. A st...
Question 38: A risk management professional is in the process of categori...
Question 39: A project manager for a large product development project as...
Question 40: Some project risks are applicable for the project ' s lifecy...
Question 41: A project has a significant impact on an organization. Multi...
Question 42: During project development, a risk manager notices that a ma...
Question 43: A project manager wants to introduce a new technology to imp...
Question 44: A subcontractor working on a project may cause delays in the...
Question 45: The project manager performed ' a variance analysis on the p...
Question 46: A risk manager is managing risks in a project. During the in...
Question 47: A project team identified some risks in a project. Team memb...
Question 48: The project manager and the risk manager of a new project to...
Question 49: A project team is presenting a delivery plan to a client. So...
Question 50: A project team has completed the risk response plan for a ne...
Question 51: In the middle of a construction project, the primary constru...
Question 52: A company manages confidential customer information, and a d...
Question 53: it typically takes 5 hours to perform a complete home inspec...
Question 54: A risk manager has identified multiple risks in an innovatio...
Question 55: A risk manager has noticed that response actions are not wor...
Question 56: The project manager leading a company ' s digital signature ...
Question 57: A project team in a multinational organization is working on...
Question 58: A project with impending risks has 12 deliverables as subpro...
Question 59: The risk manager of a major project needs to ensure the orga...
Question 60: Three months into a program, multiple workstreams are showin...
Question 61: The customer expresses concern about the increasing likeliho...
Question 62: A home solar panel project has many internal and external st...
Question 63: The project manager asks the risk manager to determine the i...
Question 64: A risk manager wants to determine what risk has the biggest ...
Question 65: At an oil and gas company, a major unified management inform...
Question 66: A project manager is working on a complex construction proje...
Question 67: A risk manager is assigned to a new system deployment projec...
Question 68: A company is preparing a formal response to bid for an infra...
Question 69: During the early planning stages of an AI-based software dev...
Question 70: During a meeting to develop the risk management plan, the ri...
Question 71: In reviewing the team ' s identified project risks, a projec...
Question 72: A project team successfully implemented a risk response plan...
Question 73: A project manager realizes the team undertaking the project ...
Question 74: In a complex project, individual risks have been identified ...
Question 75: During project planning, a risk is identified for which the ...
Question 76: A new risk manager has been hired on a project and meets wit...
Question 77: The project team is updating the risk register with the mini...
Question 78: A stakeholder is asking a project team to hire an external v...
Question 79: A new project is about to start, and the risk manager wants ...
Question 80: A project manager of an IT company is assigned to a project ...
Question 81: There is a debate within the organization on whether project...
Question 82: A project manager works on a long-term and high visibility p...
Question 83: A project manager wants to work on understanding the project...
Question 84: The risk manager for a large-scale software development proj...
Question 85: A project has consistently been lagging in cost performance ...
Question 86: A project team is concerned about a risk which, if occurs, m...
Question 87: A large, land-based infrastructure project has begun. The pr...
Question 88: A critical piece of equipment broke during a project executi...
Question 89: A project team has just initiated a large project to move an...
Question 90: The project manager has completed four projects all with sim...
Question 91: A project ' s design has been completed and approved on time...
Question 92: A project manager is educating the project team on risk mana...
Question 93: A project team identifies that there is a probability of mis...
Question 94: In the early stages of a manufacturing project, a risk manag...
Question 95: Some engineers are completing an activity that will alert th...
Question 96: A risk manager is integrated into a team overseeing a crucia...
Question 97: An organization is embarking on a multi-million-dollar proje...
Question 98: The project risk manager for an environmental preservation p...
Question 99: The project risk manager is in the process of identifying ri...
Question 100: A project manager is working on a high priority and high pro...
Question 101: An organization faces immense competition in the market and ...
Question 102: A project team has failed to complete an important project m...
Question 103: An organization with a portfolio of unique business function...
Question 104: During the weekly project meeting a risk manager identified ...
Question 105: Towards the end of definitive design, project costs have inc...
Question 106: An organization with a large computer network identified a p...
Question 107: A project manager is working on a construction project. Base...
Question 108: A complex infrastructure construction project consisting of ...
Question 109: An organization performs an annual strategies and initiative...
Question 110: A budget change request was initiated by a functional manage...
Question 111: A software development project team was preparing for a phas...
Question 112: A risk manager is tasked with establishing a risk management...
Question 113: When approving the risk contingency budget for a project, th...
Question 114: After starting a new pipeline project, a risk manager schedu...
Question 115: In the middle of a project to improve internal workflows, th...
Question 116: An eco-friendly sustainable textile-dyeing project has begun...
Question 117: A project team is developing a software system for a financi...
Question 118: During project execution for a software development program,...
Question 119: The project risk manager on a large firm fixed priced (FFP) ...
Question 120: A risk manager is confident that they have identified and qu...
Question 121: During the construction of a housing development, a project ...
Question 122: A risk manager is assigned to a mobile network deployment pr...
Question 123: A key project is delayed and all contingency reserves have b...