After identifying new risk events during a project, the project manager s NEXT step should be to:
Correct Answer: B
After identifying new risk events during a project, the project manager's next step should be to record the scenarios into the risk register, which is a document that records and tracks the identified risks, their causes, impacts, likelihood, responses, owners, and status. Recording the scenarios into the risk register helps to document and communicate the risks to the project team and stakeholders, and to facilitate the subsequent risk analysis and response processes. The other options are not the next steps, but rather the subsequent steps after recording the scenarios into the risk register. Determining if the scenarios need to be accepted or responded to is part of the risk evaluation and treatment process, which requires a prior risk analysis. Continuing with a qualitative or quantitative risk analysis is part of the risk assessment process, which requires a prior risk identification and documentation. References = Risk Register: A Project Manager's Guide with Examples [2023] * Asana; Risk Identification in Project Management; 6.3. The 5 Steps of the Risk Management Process